Installation of the Wall Disconnect Box (WDB)
TASK 23-33-47-400-803-A
Installation of the Wall Disconnect Box (WDB)
Self explanatory
2. Job Set-up Information
A. Referenced Information
3. Job Set-up
Subtask 23-33-47-865-063-A ** ON A/C NOT FOR ALL
Subtask 23-33-47-420-052-A ** ON A/C NOT FOR ALL
Subtask 23-33-47-410-052-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:12:08 UTC
Installation of the Wall Disconnect Box (WDB)
FIN: 50MK1 ** ON A/C NOT FOR ALL
FIN: 50MK2 ** ON A/C NOT FOR ALL
FIN: 50MK3 ** ON A/C NOT FOR ALL
FIN: 50MK4 ** ON A/C NOT FOR ALL
FIN: 50MK5 ** ON A/C NOT FOR ALL
FIN: 50MK6 ** ON A/C NOT FOR ALL
FIN: 50MK7 ** ON A/C NOT FOR ALL
FIN: 50MK8 ** ON A/C NOT FOR ALL
1. Reason for the JobFIN: 50MK2 ** ON A/C NOT FOR ALL
FIN: 50MK3 ** ON A/C NOT FOR ALL
FIN: 50MK4 ** ON A/C NOT FOR ALL
FIN: 50MK5 ** ON A/C NOT FOR ALL
FIN: 50MK6 ** ON A/C NOT FOR ALL
FIN: 50MK7 ** ON A/C NOT FOR ALL
FIN: 50MK8 ** ON A/C NOT FOR ALL
Self explanatory
2. Job Set-up Information
A. Referenced Information
| REFERENCE | DESIGNATION |
|---|---|
| TASK 23-33-00-710-005-A | Operational Test of the Integrated In-Flight Entertainment (IFE) System |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-23-44-000-001-A | Removal of the Lower Sidewall Panels (Dado Panels) |
| TASK 25-23-44-400-001-A | Installation of the Lower Sidewall Panels (Dado Panels) |
Subtask 23-33-47-865-063-A ** ON A/C NOT FOR ALL
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 23-33-47-860-054-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2000VU | PES-VIDEO-CONTROL-VCC-DS/C | 21MH | C02 |
| 2000VU | PES-VIDEO-CONTROL-MAIN | 20MH | C01 |
| 2000VU | PES-MUSIC-CABIN AFT-RH | 25MK | D05 |
| 2000VU | PES-MUSIC-CABIN AFT-LH | 22MK | D04 |
| 2000VU | PES-MUSIC-CABIN FWD-RH | 24MK | D03 |
| 2000VU | PES-MUSIC-CABIN FWD-LH | 23MK | D02 |
| 2000VU | PES-MUSIC - CTL | 21MK | D01 |
B. Preparation for Installation
(1) Make sure that the applicable lower sidewall panel in the area of the related WDB is removed (Ref. AMM TASK 25-23-44-000-001).
(2) Make sure that the protection cap (10) of the related WDB (8) is removed.
4. Procedure(1) Make sure that the applicable lower sidewall panel in the area of the related WDB is removed (Ref. AMM TASK 25-23-44-000-001).
(2) Make sure that the protection cap (10) of the related WDB (8) is removed.
Subtask 23-33-47-420-052-A ** ON A/C NOT FOR ALL
A. Installation of the Wall Disconnect Box (WDB)
(1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Clean the component interfaces and the adjacent area.
(3) Do an inspection of the component interfaces and the adjacent area.
(4) Put the insulation strip (7), the WDB (8) and the protective cover (13) carefully into position.
(5) Install the screws (11) and the washers (12).
(6) If applicable, install the spacers (5) and (4) and the cable support (3).
(7) Install the screw (1) and the washer (2).
(8) Remove the blanking caps from the electrical connector(s) (6).
(9) Make sure that the electrical connector(s) are clean and in the correct condition.
(10) Connect the electrical connector(s) (6) to the WDB (8) as identified during the removal procedure.
(11) Safety the electrical connector(s) (6).
Subtask 23-33-47-865-064-A ** ON A/C NOT FOR ALL (1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Clean the component interfaces and the adjacent area.
(3) Do an inspection of the component interfaces and the adjacent area.
(4) Put the insulation strip (7), the WDB (8) and the protective cover (13) carefully into position.
(5) Install the screws (11) and the washers (12).
(6) If applicable, install the spacers (5) and (4) and the cable support (3).
(7) Install the screw (1) and the washer (2).
(8) Remove the blanking caps from the electrical connector(s) (6).
(9) Make sure that the electrical connector(s) are clean and in the correct condition.
(10) Connect the electrical connector(s) (6) to the WDB (8) as identified during the removal procedure.
(11) Safety the electrical connector(s) (6).
CAUTION:
MAKE SURE THAT THE SPRING LATCHES CORRECTLY HOLD THE CONNECTOR IN THE FULLY ENGAGED POSITION. THE SPRING LATCHES PREVENT UNWANTED MOVEMENT OF THE CONNECTOR, AND THUS THE RISK OF ARCING, WHICH CAN CAUSE DAMAGE TO THE UNIT.
(12) Safety the electrical connector(s) (6) with the spring latches. B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 23-33-47-710-053-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2000VU | PES-VIDEO-CONTROL-VCC-DS/C | 21MH | C02 |
| 2000VU | PES-VIDEO-CONTROL-MAIN | 20MH | C01 |
| 2000VU | PES-MUSIC-CABIN AFT-RH | 25MK | D05 |
| 2000VU | PES-MUSIC-CABIN AFT-LH | 22MK | D04 |
| 2000VU | PES-MUSIC-CABIN FWD-RH | 24MK | D03 |
| 2000VU | PES-MUSIC-CABIN FWD-LH | 23MK | D02 |
| 2000VU | PES-MUSIC - CTL | 21MK | D01 |
C. Do the operational test of the integrated In-Flight Entertainment (IFE) system (Ref. AMM TASK 23-33-00-710-005).
5. Close-upSubtask 23-33-47-410-052-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the protection cap (10) in position and tighten the fasteners (9).
(3) Install the related lower sidewall panel (Ref. AMM TASK 25-23-44-400-001).
Subtask 23-33-47-862-052-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Put the protection cap (10) in position and tighten the fasteners (9).
(3) Install the related lower sidewall panel (Ref. AMM TASK 25-23-44-400-001).
Wall Disconnect Box