Installation of SDU Configuration Module (SCM)
TASK 23-28-32-400-802-A
Installation of SDU Configuration Module (SCM)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 23-28-32-860-051-A ** ON A/C NOT FOR ALL
Subtask 23-28-32-420-051-A ** ON A/C NOT FOR ALL
Subtask 23-28-32-410-051-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:12:03 UTC
Installation of SDU Configuration Module (SCM)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 120 | AVIONICS COMPARTMENT |
| 824 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 23-28-32-000-803-A | Removal of the SIM Card from the SDU Configuration Module (SCM) |
| TASK 23-28-32-400-803-A | Installation of the Subscriber Identity Module (SIM) Card in the Satellite Data Unit (SDU) Configuration Module (SCM) |
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
Subtask 23-28-32-860-051-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE is in position at the access door 824.
(3) Make sure that the access door 824 is open.
Subtask 23-28-32-865-054-A ** ON A/C NOT FOR ALL (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE is in position at the access door 824.
(3) Make sure that the access door 824 is open.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | SATCOM | 240RV | K01 |
Subtask 23-28-32-420-051-A ** ON A/C NOT FOR ALL
A. Installation of the SDU Configuration Module (SCM)
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the CAP-BLANKING from each electrical connector and receptacle.
(4) Make sure that all the electrical connections are clean and in the correct condition.
(5) Install the SCM (3) with the screws (2) and the washers (1).
(6) Connect the connector (4).
(7) If necessary, remove the new SIM card from the new SCM and install the SIM card retained during the removal procedure in the SCM (Ref. AMM TASK 23-28-32-000-803) (Ref. AMM TASK 23-28-32-400-803).
Subtask 23-28-32-865-055-A ** ON A/C NOT FOR ALL (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the CAP-BLANKING from each electrical connector and receptacle.
(4) Make sure that all the electrical connections are clean and in the correct condition.
(5) Install the SCM (3) with the screws (2) and the washers (1).
(6) Connect the connector (4).
(7) If necessary, remove the new SIM card from the new SCM and install the SIM card retained during the removal procedure in the SCM (Ref. AMM TASK 23-28-32-000-803) (Ref. AMM TASK 23-28-32-400-803).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 23-28-32-740-051-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | SATCOM | 240RV | K01 |
C. BITE Test with the Multipurpose Control and Display Unit (MCDU)
5. Close-up| ACTION | RESULT |
|---|---|
| 1.On the MCDU, on the MCDU MENU page: | On the MCDU: |
|
|
| 2.On the SATCOM MAIN MENU page: | |
|
|
| 3.On the SATCOM STATUS page: | |
|
|
Subtask 23-28-32-410-051-A ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration.
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824.
(3) Remove the access platform(s).
Subtask 23-28-32-862-051-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824.
(3) Remove the access platform(s).
SDU Configuration Module (SCM)