Replacement of the Hose


TASK 21-52-32-960-801-A
Replacement of the Hose


WARNING: MAKE SURE THAT AIR IS NOT SUPPLIED TO THE AIR CONDITIONING SYSTEM FROM THE MAIN ENGINE, THE APU OR A GROUND SOURCE. HOT COMPRESSED AIR CAN CAUSE INJURY TO PERSONNEL.
NOTE: The procedure is the same for condensers 10HM2 and 11HM2.
ZONE: 191
ZONE: 192
1. Reason for the Job
NOTE: The procedure is only applicable when the hose is installed.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
SAFETY CLIP - CIRCUIT BREAKER
No specific
Torque wrench: range to between 0.1 and 0.05 m.daN (8.85 and 4.42 lbf.in ) T
No specific
Torque wrench: range to between 0.28 and 0.26 m.daN (24.78 and 23.01 lbf.in ) T
No specific
Torque wrench: range to between 0.67 and 0.55 m.daN (59.29 and 48.67 lbf.in ) T
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
191
AIR CONDITIONING COMPT AND FAIRINGS
192
AIR CONDITIONING COMPT AND FAIRINGS
FOR [10HM2] (CONDENSER)
191BB, 191KB
FOR [11HM2] (CONDENSER)
192FB, 192KB
 C. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
2
HOSE
AIPC 21-52-32-02-010
4
CLAMP
AIPC 21-52-32-02-020
5
SCREW
AIPC 21-52-32-02-040
6
WASHER
AIPC 21-52-32-02-050
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 12-33-21-618-001-A-01
Pre-conditioning through the HP Ground Connection
TASK 12-33-21-618-001-A-02
Pre-conditioning with the APU
TASK 21-63-00-710-004-A
Operational Test of the Cockpit and Cabin Temperature Control with CFDS/MCDU
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 53-35-13-000-002-A
Removal of the Quick-Release Access Panels from the Belly Fairing Structure
TASK 53-35-13-400-002-A
Installation of the Quick-Release Access Panels on the Belly Fairing Structure
3. Job Set-up
Subtask 21-52-32-861-052-A
A. Energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-861-002).
Subtask 21-52-32-865-054-A
B. Open, safety and tag this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
FOR FIN: 10HM2 (CONDENSER)
49VUAIR COND/TEMP CTL/SYS 1 CHAN B/28VDC52HHD08
** ON A/C NOT FOR ALL
122VUAIR COND/PACK TEMP/CTL SYS1/1/115VAC1HHX22
122VUAIR COND/PACK TEMP/CTL SYS1/1/28VDC3HHX21
122VUAIR COND/PACK TEMP CTL SYS2/1/28VDC4HHY19
122VUAIR COND/PACK TEMP CTL SYS2/1/115VAC2HHY18
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 1/CHAN A/115VAC49HHX22
122VUAIR COND/TEMP CTL SYS 1/CHAN A/28VDC51HHX21
122VUAIR COND/TEMP CTL SYS 1/CHAN B/115VAC50HHY18
** ON A/C NOT FOR ALL
FOR FIN: 11HM2 (CONDENSER)
122VUAIR COND/PACK TEMP/CTL SYS1/2/115VAC21HHW22
122VUAIR COND/PACK TEMP/CTL SYS1/2/28VDC23HHW21
122VUAIR COND/PACK TEMP CTL SYS2/2/28VDC24HHY21
122VUAIR COND/PACK TEMP CTL SYS2/2/115VAC22HHY20
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 2/CHAN A/115VAC53HHW22
122VUAIR COND/TEMP CTL SYS 2/CHAN A/28VDC55HHW21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/28VDC56HHY21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/115VAC54HHY20
Subtask 21-52-32-010-051-A
C. Get Access
   (1) Remove the access panel(s) (Ref. AMM TASK 53-35-13-000-002):
     (a) FOR [10HM2] (CONDENSER)
     (b) FOR [11HM2] (CONDENSER)
4. Procedure
Subtask 21-52-32-960-050-A Subtask 21-52-32-865-055-A
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
FOR FIN: 10HM2 (CONDENSER)
49VUAIR COND/TEMP CTL/SYS 1 CHAN B/28VDC52HHD08
** ON A/C NOT FOR ALL
122VUAIR COND/PACK TEMP/CTL SYS1/1/115VAC1HHX22
122VUAIR COND/PACK TEMP/CTL SYS1/1/28VDC3HHX21
122VUAIR COND/PACK TEMP CTL SYS2/1/28VDC4HHY19
122VUAIR COND/PACK TEMP CTL SYS2/1/115VAC2HHY18
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 1/CHAN A/115VAC49HHX22
122VUAIR COND/TEMP CTL SYS 1/CHAN A/28VDC51HHX21
122VUAIR COND/TEMP CTL SYS 1/CHAN B/115VAC50HHY18
** ON A/C NOT FOR ALL
FOR FIN: 11HM2 (CONDENSER)
122VUAIR COND/PACK TEMP/CTL SYS1/2/115VAC21HHW22
122VUAIR COND/PACK TEMP/CTL SYS1/2/28VDC23HHW21
122VUAIR COND/PACK TEMP CTL SYS2/2/28VDC24HHY21
122VUAIR COND/PACK TEMP CTL SYS2/2/115VAC22HHY20
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 2/CHAN A/115VAC53HHW22
122VUAIR COND/TEMP CTL SYS 2/CHAN A/28VDC55HHW21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/28VDC56HHY21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/115VAC54HHY20
Subtask 21-52-32-710-051-A
C. Test
   (1) Do the pre-conditioning through the HP ground connector (
Ref. AMM TASK 12-33-21-618-001) or with the APU (Ref. AMM TASK 12-33-21-618-001).
   (2) Do a leak check of the condenser connections.
NOTE: Minimum leakage is permitted. After the pack operates for some minutes, the leakage of air will decrease because the seals have their correct operating temperature.
   (3) Do a leak check of the sense line connections:
     (a) Make sure that there are no leaks.
   (4) After approximately 15 minutes, stop the pre-conditioning (Ref. AMM TASK 12-33-21-618-001) or (Ref. AMM TASK 12-33-21-618-001).
   (5) Do the operational test of the cockpit and cabin temperature control (Ref. AMM TASK 21-63-00-710-004).
5. Close-up
Subtask 21-52-32-410-052-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the access panel(s) (Ref. AMM TASK 53-35-13-400-002):
     (a) FOR [10HM2] (CONDENSER)
     (b) FOR [11HM2] (CONDENSER)
   (3) Remove the WARNING NOTICE(S).
Subtask 21-52-32-862-051-A
B. De-energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-862-002).