Removal of the Primary Heat Exchanger


TASK 21-52-25-000-001-A
Removal of the Primary Heat Exchanger


WARNING: MAKE SURE THAT AIR IS NOT SUPPLIED TO THE AIR CONDITIONING SYSTEM FROM THE MAIN ENGINE, THE APU OR A GROUND SOURCE. HOT COMPRESSED AIR CAN CAUSE INJURY TO PERSONNEL.
NOTE: The procedure is the same for the primary heat exchanger 10HM6 and 11HM6.
FIN: 10HM6
FIN: 11HM6
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
SAFETY CLIP - CIRCUIT BREAKER
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
FOR [10HM6] (HEAT EXCHANGER-PRIMARY)
191KB
FOR [11HM6] (HEAT EXCHANGER-PRIMARY)
192KB
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 21-52-24-000-001-A
Removal of the Heat Exchanger Unit (from the Aircraft)
TASK 21-52-24-000-001-A-01
Removal of the Heat Exchanger Unit (From the Air Conditioning Pack)
TASK 53-35-13-000-002-A
Removal of the Quick-Release Access Panels from the Belly Fairing Structure
3. Job Set-up
Subtask 21-52-25-865-050-A
A. Open, safety and tag this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
FOR FIN: 10HM6 (HEAT EXCHANGERPRIMARY)
49VUAIR COND/TEMP CTL/SYS 1 CHAN B/28VDC52HHD08
** ON A/C NOT FOR ALL
122VUAIR COND/PACK TEMP/CTL SYS1/1/115VAC1HHX22
122VUAIR COND/PACK TEMP/CTL SYS1/1/28VDC3HHX21
122VUAIR COND/PACK TEMP CTL SYS2/1/28VDC4HHY19
122VUAIR COND/PACK TEMP CTL SYS2/1/115VAC2HHY18
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 1/CHAN A/115VAC49HHX22
122VUAIR COND/TEMP CTL SYS 1/CHAN A/28VDC51HHX21
122VUAIR COND/TEMP CTL SYS 1/CHAN B/115VAC50HHY18
** ON A/C NOT FOR ALL
FOR FIN: 11HM6 (HEAT EXCHANGERPRIMARY)
122VUAIR COND/PACK TEMP/CTL SYS1/2/115VAC21HHW22
122VUAIR COND/PACK TEMP/CTL SYS1/2/28VDC23HHW21
122VUAIR COND/PACK TEMP CTL SYS2/2/28VDC24HHY21
122VUAIR COND/PACK TEMP CTL SYS2/2/115VAC22HHY20
** ON A/C NOT FOR ALL
122VUAIR COND/TEMP CTL SYS 2/CHAN A/115VAC53HHW22
122VUAIR COND/TEMP CTL SYS 2/CHAN A/28VDC55HHW21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/28VDC56HHY21
122VUAIR COND/TEMP CTL SYS 2/CHAN B/115VAC54HHY20
Subtask 21-52-25-010-050-A
B. Get Access
   (1) Remove the access panel/s (Ref. AMM TASK 53-35-13-000-002).
     (a) FOR [10HM6] (HEAT EXCHANGER-PRIMARY)
     (b) FOR [11HM6] (HEAT EXCHANGER-PRIMARY)
4. Procedure
Subtask 21-52-25-020-050-A
A. Removal of the Primary Heat Exchanger
   (1) Remove the heat exchanger unit (Ref. AMM TASK 21-52-24-000-001).
   (2) Remove the screws (2), washers (3), fan plenum (1) and gasket (4) (if installed).
   (3) Remove the screws (8), the washers (7) and the primary heat exchanger (5).
   (4) Remove the gasket (6) (if installed).
   (5) Put the protective covers on the cooling elements of the primary heat exchanger (5) and the main heat exchanger (9).