Removal of the Pipe Assembly between the Main Heat Exchanger and the Air Cycle Machine
TASK 21-52-23-000-001-A
Removal of the Pipe Assembly between the Main Heat Exchanger and the Air Cycle Machine
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 21-52-23-861-055-A Subtask 21-52-23-865-050-A
Subtask 21-52-23-020-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:11:27 UTC
Removal of the Pipe Assembly between the Main Heat Exchanger and the Air Cycle Machine
WARNING:
MAKE SURE THAT AIR IS NOT SUPPLIED TO THE AIR CONDITIONING SYSTEM FROM THE MAIN ENGINE, THE APU OR A GROUND SOURCE.
HOT COMPRESSED AIR CAN CAUSE INJURY TO PERSONNEL.
WARNING:
USE PROTECTIVE GOGGLES AND GLOVES WHEN YOU REMOVE OR INSTALL LOCKWIRE. EACH TIME YOU CUT LOCKWIRE, REMOVE AND DISCARD IT IMMEDIATELY. LOOSE LOCKWIRE CAN CUT YOU OR MAKE YOU BLIND, AND/OR CAN CAUSE DAMAGE.
NOTE: The procedure for the removal of the pipe assembly is the same for the left and right side.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | CAP - BLANKING |
| No specific | AR | PLUG - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| FOR [10HM] (PACK 1-AIR CONDITIONING) | |
| 191KB | |
| FOR [11HM] (PACK 2-AIR CONDITIONING) | |
| 192KB | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 53-35-13-000-002-A | Removal of the Quick-Release Access Panels from the Belly Fairing Structure |
Subtask 21-52-23-861-055-A Subtask 21-52-23-865-050-A
B. Open, safety and tag this(these) circuit breaker(s):
Subtask 21-52-23-010-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| FOR FIN: 10HM (PACK 1AIR CONDITIONING) | |||
| 49VU | AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC | 52HH | D08 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR COND/PACK TEMP/CTL SYS1/1/115VAC | 1HH | X22 |
| 122VU | AIR COND/PACK TEMP/CTL SYS1/1/28VDC | 3HH | X21 |
| 122VU | AIR COND/PACK TEMP CTL SYS2/1/28VDC | 4HH | Y19 |
| 122VU | AIR COND/PACK TEMP CTL SYS2/1/115VAC | 2HH | Y18 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN A/115VAC | 49HH | X22 |
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN A/28VDC | 51HH | X21 |
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN B/115VAC | 50HH | Y18 |
| ** ON A/C NOT FOR ALL | |||
| FOR FIN: 11HM (PACK 2AIR CONDITIONING) | |||
| 122VU | AIR COND/PACK TEMP/CTL SYS1/2/115VAC | 21HH | W22 |
| 122VU | AIR COND/PACK TEMP/CTL SYS1/2/28VDC | 23HH | W21 |
| 122VU | AIR COND/PACK TEMP CTL SYS2/2/28VDC | 24HH | Y21 |
| 122VU | AIR COND/PACK TEMP CTL SYS2/2/115VAC | 22HH | Y20 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN A/115VAC | 53HH | W22 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN A/28VDC | 55HH | W21 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN B/28VDC | 56HH | Y21 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN B/115VAC | 54HH | Y20 |
C. Get Access
(1) Remove the access panel (Ref. AMM TASK 53-35-13-000-002):
(a) FOR [10HM] (PACK 1-AIR CONDITIONING)
(b) FOR [11HM] (PACK 2-AIR CONDITIONING)
Subtask 21-52-23-941-050-A (1) Remove the access panel (Ref. AMM TASK 53-35-13-000-002):
(a) FOR [10HM] (PACK 1-AIR CONDITIONING)
(b) FOR [11HM] (PACK 2-AIR CONDITIONING)
D. Safety Precautions
(1) On the overhead panel, on AIR COND panel 30VU:
(a) Make sure that:
(2) On the HP ground connector, put the WARNING NOTICE(S) in position to tell persons not to supply the ground air.
4. Procedure(1) On the overhead panel, on AIR COND panel 30VU:
(a) Make sure that:
- The APU BLEED pushbutton switch is released (the ON legend is off).
- The ENG 1 BLEED and the ENG 2 BLEED pushbutton switches are released (the OFF legends are on).
(2) On the HP ground connector, put the WARNING NOTICE(S) in position to tell persons not to supply the ground air.
Subtask 21-52-23-020-050-A ** ON A/C NOT FOR ALL
A. Removal of the Pipe Assembly
(1) Disconnect the electrical connectors (9) and (17).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Disconnect the sense line connector (6).
(4) Put the PLUG-BLANKING in each disconnected line end.
(5) Before you remove the nuts (1), hold the hexagon part of the retaining cables (3) to prevent twisting of the retaining cables (3).
(6) Remove and discard the nuts (1) and the washers (2) and disconnect the retaining cables (3).
(7) Remove and discard the lockwire from the clamp (15).
(8) Remove the clamp (15) and the half-clamps (12).
(9) Hold the pipe assembly (21) and move the sleeve (16) away from the packings (14) onto the air-cycle machine outlet (13).
(10) Carefully remove the pipe assembly (21) from the sleeve (4) and the air-cycle machine outlet (13).
(11) Remove and discard the seal (5).
(12) Remove the sleeve (16).
(13) Remove and discard the packings (14).
(14) Put the PLUG-BLANKING in each disconnected line end.
Subtask 21-52-23-020-050-C ** ON A/C NOT FOR ALL (1) Disconnect the electrical connectors (9) and (17).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Disconnect the sense line connector (6).
(4) Put the PLUG-BLANKING in each disconnected line end.
(5) Before you remove the nuts (1), hold the hexagon part of the retaining cables (3) to prevent twisting of the retaining cables (3).
(6) Remove and discard the nuts (1) and the washers (2) and disconnect the retaining cables (3).
(7) Remove and discard the lockwire from the clamp (15).
(8) Remove the clamp (15) and the half-clamps (12).
(9) Hold the pipe assembly (21) and move the sleeve (16) away from the packings (14) onto the air-cycle machine outlet (13).
(10) Carefully remove the pipe assembly (21) from the sleeve (4) and the air-cycle machine outlet (13).
(11) Remove and discard the seal (5).
(12) Remove the sleeve (16).
(13) Remove and discard the packings (14).
(14) Put the PLUG-BLANKING in each disconnected line end.
A. Removal of the Pipe Assembly
(1) Disconnect the electrical connector (6).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Before you remove the nuts (1), hold the hexagon part of the retaining cables (3) to prevent twisting of the retaining cables (3).
(4) Remove and discard the nuts (1) and the washers (2) and disconnect the retaining cables (3).
(5) Remove and discard the lockwire from the clamp (13).
(6) Remove the clamp (13) and the half-clamps (10).
(7) Hold the pipe assembly (9) and move the sleeve (14) away from the packings (12) onto the air-cycle machine outlet (11).
(8) Carefully remove the pipe assembly (9) from the sleeve (4).
(9) Remove and discard the seal (5).
(10) Remove the sleeve (14).
(11) Remove and discard the packings (12).
(12) Put the PLUG-BLANKING in each disconnected line end.
(1) Disconnect the electrical connector (6).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Before you remove the nuts (1), hold the hexagon part of the retaining cables (3) to prevent twisting of the retaining cables (3).
(4) Remove and discard the nuts (1) and the washers (2) and disconnect the retaining cables (3).
(5) Remove and discard the lockwire from the clamp (13).
(6) Remove the clamp (13) and the half-clamps (10).
(7) Hold the pipe assembly (9) and move the sleeve (14) away from the packings (12) onto the air-cycle machine outlet (11).
(8) Carefully remove the pipe assembly (9) from the sleeve (4).
(9) Remove and discard the seal (5).
(10) Remove the sleeve (14).
(11) Remove and discard the packings (12).
(12) Put the PLUG-BLANKING in each disconnected line end.
Pipe Assembly - Component Location