Removal of the Air Outlet Heater
TASK 21-41-51-000-001-A
Removal of the Air Outlet Heater
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 21-41-51-861-050-A ** ON A/C NOT FOR ALL Subtask 21-41-51-010-050-A ** ON A/C NOT FOR ALL
Subtask 21-41-51-020-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:11:17 UTC
Removal of the Air Outlet Heater
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| No specific | AR | CAP - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 811 | |
| FOR [3HE] (HEATER-AIR OUTLET, L) | |
| 211AW, 211BZ | |
| FOR [4HE] (HEATER-AIR OUTLET, R) | |
| 212AW, 212BZ | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 25-13-41-000-002-A | Removal of the Sidewall Panels |
Subtask 21-41-51-861-050-A ** ON A/C NOT FOR ALL Subtask 21-41-51-010-050-A ** ON A/C NOT FOR ALL
B. Get Access
(1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at the access door 811.
(2) Open the access door 811.
Subtask 21-41-51-865-053-A ** ON A/C NOT FOR ALL (1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at the access door 811.
(2) Open the access door 811.
C. Open, safety and tag this(these) circuit breaker(s):
Subtask 21-41-51-010-051-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 122VU | CKPT/FOOT/HEATERS | 1HE | V23 |
D. Get Access
(1) In the cockpit, remove the sidewall panels as necessary (Ref. AMM TASK 25-13-41-000-002):
(a) FOR [3HE] (HEATER-AIR OUTLET, L)
211BZ 211AW
(b) FOR [4HE] (HEATER-AIR OUTLET, R)
212BZ 212AW
Subtask 21-41-51-941-050-A ** ON A/C NOT FOR ALL (1) In the cockpit, remove the sidewall panels as necessary (Ref. AMM TASK 25-13-41-000-002):
(a) FOR [3HE] (HEATER-AIR OUTLET, L)
211BZ 211AW
(b) FOR [4HE] (HEATER-AIR OUTLET, R)
212BZ 212AW
E. Safety Precautions
(1) On the AIR COND panel 30VU:
(a) Make sure that:
(2) On the HP and LP ground connectors, put a WARNING NOTICE(S) in position to tell persons not to supply the ground source.
4. Procedure(1) On the AIR COND panel 30VU:
(a) Make sure that:
- The APU BLEED pushbutton switch is released
- The ENG 1 BLEED and ENG 2 BLEED pushbutton switches are released
- The PACK 1 and PACK 2 pushbutton switches are released.
(2) On the HP and LP ground connectors, put a WARNING NOTICE(S) in position to tell persons not to supply the ground source.
Subtask 21-41-51-020-050-A ** ON A/C NOT FOR ALL
A. Removal of the Air Outlet Heater
(1) Disconnect the electrical connector (6).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Remove the clamp (4) and the duct (5) from the air outlet heater (2).
(4) Remove the four screws (7), washers (8) and nuts (9).
(5) Remove the clamp (3).
(6) Remove the air outlet heater (2).
(1) Disconnect the electrical connector (6).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Remove the clamp (4) and the duct (5) from the air outlet heater (2).
(4) Remove the four screws (7), washers (8) and nuts (9).
(5) Remove the clamp (3).
(6) Remove the air outlet heater (2).