Installation of the Ventilation Controller
TASK 21-28-34-400-001-A
Installation of the Ventilation Controller
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 21-28-34-860-050-A ** ON A/C NOT FOR ALL
Subtask 21-28-34-420-050-A ** ON A/C NOT FOR ALL
Subtask 21-28-34-410-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:11:11 UTC
Installation of the Ventilation Controller
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 126 | LATERAL AVIONIC COMPARTMENT |
| 822 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 21-28-00-720-003-A | Functional Test of the FWD Cargo-Compartment Ventilation-System |
| TASK 21-28-00-720-004-A | Functional Test of the AFT Cargo-Compartment Ventilation-System |
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
Subtask 21-28-34-860-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
Subtask 21-28-34-865-051-A ** ON A/C NOT FOR ALL (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 21-28-34-010-051-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/AFT CARGO/VENT/CTL & MONG | 31HN | C07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/AFT CARGO/VENT & HTG/CTL & MONG | 31HN | C07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/FWD CARGO/VENT/CTL & MONG | 2HN | C08 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR COND/AFT CARGO VENT/FAN | 30HN | S22 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | FWD CARGO VENT AND HTG/FAN | 1HN | T22 |
C. Get Access
(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position under the lateral avionics compartment door 822.
(2) Make sure that the access door 822 is open.
4. Procedure(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position under the lateral avionics compartment door 822.
(2) Make sure that the access door 822 is open.
Subtask 21-28-34-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Ventilation Controller
(1) Install the ventilation controller (1).
(2) Install and tighten the nuts (2).
(3) Remove the CAP-BLANKING from each electrical connector and receptacle.
(4) Make sure that all the electrical connections are clean and in the correct condition.
(5) Connect the electrical connector(s) (3).
Subtask 21-28-34-865-052-A ** ON A/C NOT FOR ALL (1) Install the ventilation controller (1).
(2) Install and tighten the nuts (2).
(3) Remove the CAP-BLANKING from each electrical connector and receptacle.
(4) Make sure that all the electrical connections are clean and in the correct condition.
(5) Connect the electrical connector(s) (3).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 21-28-34-720-050-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/AFT CARGO/VENT/CTL & MONG | 31HN | C07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/AFT CARGO/VENT & HTG/CTL & MONG | 31HN | C07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/FWD CARGO/VENT/CTL & MONG | 2HN | C08 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR COND/AFT CARGO VENT/FAN | 30HN | S22 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | FWD CARGO VENT AND HTG/FAN | 1HN | T22 |
C. Do a functional test of the FWD cargo compartment ventilation system (Ref. AMM TASK 21-28-00-720-003).
Subtask 21-28-34-720-050-B ** ON A/C NOT FOR ALL C. Do a functional test of the AFT cargo compartment ventilation system (Ref. AMM TASK 21-28-00-720-004).
5. Close-upSubtask 21-28-34-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 822.
(3) Remove the access platform(s).
Subtask 21-28-34-862-050-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 822.
(3) Remove the access platform(s).
Ventilation Controller