Operational Test of the FWD Cargo-Compartment Ventilation-System
TASK 21-28-00-710-005-A
Operational Test of the FWD Cargo-Compartment Ventilation-System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 21-28-00-861-069-A ** ON A/C NOT FOR ALL Subtask 21-28-00-865-071-A ** ON A/C NOT FOR ALL
Subtask 21-28-00-710-058-A ** ON A/C NOT FOR ALL
Subtask 21-28-00-410-065-D ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:11:11 UTC
Operational Test of the FWD Cargo-Compartment Ventilation-System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 131QW, 132KW |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 25-54-12-000-003-A | Removal of the Sidewall Panels in the Forward Cargo Compartment |
| TASK 25-54-12-400-003-A | Installation of the Sidewall Panels in the Forward Cargo Compartment |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-30-00-860-002-A | Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
Subtask 21-28-00-861-069-A ** ON A/C NOT FOR ALL Subtask 21-28-00-865-071-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 21-28-00-010-064-D ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR COND/FWD CARGO/VENT/CTL & MONG | 2HN | C08 |
| 49VU | AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC | 52HH | D08 |
| 122VU | FWD CARGO VENT AND HTG/FAN | 1HN | T22 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN A/115VAC | 53HH | W22 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN A/28VDC | 55HH | W21 |
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN A/115VAC | 49HH | X22 |
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN A/28VDC | 51HH | X21 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN B/28VDC | 56HH | Y21 |
| 122VU | AIR COND/TEMP CTL SYS 2/CHAN B/115VAC | 54HH | Y20 |
| 122VU | AIR COND/TEMP CTL SYS 1/CHAN B/115VAC | 50HH | Y18 |
C. Get Access
(1) Open the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
(2) Put the ACCESS PLATFORM 2M (6 FT) in position at the FWD cargo-compartment door 825.
(3) Remove the access panels 132KW and 131QW (Ref. AMM TASK 25-54-12-000-003).
Subtask 21-28-00-860-054-A ** ON A/C NOT FOR ALL (1) Open the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
(2) Put the ACCESS PLATFORM 2M (6 FT) in position at the FWD cargo-compartment door 825.
(3) Remove the access panels 132KW and 131QW (Ref. AMM TASK 25-54-12-000-003).
D. Aircraft Maintenance Configuration
(1) On the overhead panel 22VU make sure that the white OFF light in the FWD ISOL VALVE pushbutton switch is on.
4. Procedure(1) On the overhead panel 22VU make sure that the white OFF light in the FWD ISOL VALVE pushbutton switch is on.
Subtask 21-28-00-710-058-A ** ON A/C NOT FOR ALL
A. Do the Operational Test of the Ventilation System
5. Close-upNOTE: During the test you must visually monitor the inlet and the outlet isolation valves for the correct movement sequence.
| ACTION | RESULT |
|---|---|
1.On the panel 22VU:
| On the panel 22VU:
|
| | In the FWD cargo compartment:
|
2.On the panel 22VU:
| On the panel 22VU:
|
| | In the FWD cargo compartment:
|
Subtask 21-28-00-410-065-D ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panels 132KW and 131QW (Ref. AMM TASK 25-54-12-400-003).
(3) Remove the access platform(s).
(4) Close the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
Subtask 21-28-00-862-065-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panels 132KW and 131QW (Ref. AMM TASK 25-54-12-400-003).
(3) Remove the access platform(s).
(4) Close the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).