Installation of the Avionics Equipment Blowing-Duct
TASK 21-26-42-400-802-A
Installation of the Avionics Equipment Blowing-Duct
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 21-26-42-860-060-A
Subtask 21-26-42-420-060-A
Subtask 21-26-42-410-062-A
[Rev.10 from 2021]
2026.04.02 06:11:05 UTC
Installation of the Avionics Equipment Blowing-Duct
CAUTION:
USE ONLY THE GROUND SERVICE NETWORK TO SUPPLY ELECTRICITY BECAUSE THE AVIONICS VENTILATION SYSTEM IS NOT SERVICEABLE. IF YOU ENERGIZE THE AIRCRAFT ELECTRICAL CIRCUITS WITHOUT THE VENTILATION SYSTEM YOU WILL CAUSE DAMAGE TO ELECTRICAL EQUIPMENT.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 120 | AVIONICS COMPARTMENT |
| 130 | FWD CARGO COMPT AFT BULKHEAD OF AVNCS COMPT TO FWD PRESSURE BULKHEAD OF WING CENTER BOX |
| 131CW, 131DW, 131GW, 131HW |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 21-26-00-710-001-A | Operational Check of the Avionics Equipment Ventilation-System via MCDU |
| TASK 21-26-00-710-001-A-01 | Operational Check of the Avionics Equipment Ventilation (without the CFDS) |
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-54-11-000-001-A | Removal of the Forward Cargo-Compartment Partition FR24A |
| TASK 25-54-11-400-001-A | Installation of the Forward Cargo-Compartment Partition FR24A |
| TASK 25-54-12-000-003-A | Removal of the Sidewall Panels in the Forward Cargo Compartment |
| TASK 25-54-12-400-003-A | Installation of the Sidewall Panels in the Forward Cargo Compartment |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
Subtask 21-26-42-860-060-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001).
(2) On AIR COND panel 30VU:
(a) Make sure that the APU BLEED, all ENG BLEED and PACK 1(2) pushbutton switches are released.
(b) Make sure that the WARNING NOTICE(S) is(are) in position to tell persons not to operate these pushbutton switches.
(3) On the HP and the LP ground connectors, make sure that the WARNING NOTICE(S) is(are) in position to tell persons not to supply the ground air sources.
Subtask 21-26-42-865-063-A (1) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001).
(2) On AIR COND panel 30VU:
(a) Make sure that the APU BLEED, all ENG BLEED and PACK 1(2) pushbutton switches are released.
(b) Make sure that the WARNING NOTICE(S) is(are) in position to tell persons not to operate these pushbutton switches.
(3) On the HP and the LP ground connectors, make sure that the WARNING NOTICE(S) is(are) in position to tell persons not to supply the ground air sources.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 21-26-42-010-066-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | AIR COND/AVNCS VENT/CTL | 6HQ | D06 |
| 49VU | AIR COND/AVNCS VENT/CTL | 5HQ | D05 |
| 122VU | AIR COND/AVNCS/VENT/MONG | 3HQ | Y17 |
| ** ON A/C NOT FOR ALL | |||
| 123VU | AVNCS VENT/EXTC/FAN | 2HQ | AE02 |
| ** ON A/C ALL | |||
| 123VU | AVNCS VENT/BLOWER/FAN | 1HQ | AD10 |
| ** ON A/C NOT FOR ALL | |||
| 123VU | AVNCS VENT/EXTC/FAN | 2HQ | AC04 |
C. Get Access
(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position below the forward cargo-compartment door.
(2) Make sure that the forward cargo-compartment door is open (Ref. AMM TASK 52-30-00-860-001).
(3) Make sure that forward cargo-compartment partition-panels 131CW and 131DW are removed (Ref. AMM TASK 25-54-11-000-001).
(4) Make sure that forward cargo-compartment sidewall-panels 131GW and 131HW are removed (Ref. AMM TASK 25-54-12-000-003).
4. Procedure(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position below the forward cargo-compartment door.
(2) Make sure that the forward cargo-compartment door is open (Ref. AMM TASK 52-30-00-860-001).
(3) Make sure that forward cargo-compartment partition-panels 131CW and 131DW are removed (Ref. AMM TASK 25-54-11-000-001).
(4) Make sure that forward cargo-compartment sidewall-panels 131GW and 131HW are removed (Ref. AMM TASK 25-54-12-000-003).
Subtask 21-26-42-420-060-A
A. Installation of the Avionics Equipment Blowing-Duct
(1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Make sure that the clamps (3), (5) and (7), the flexible sleeves (6) and the ducts (1), (2) and (4) are in the correct condition.
(3) Remove the PLUG-BLANKING from each disconnected line end.
(4) Install the flexible sleeves (6) on the ducts (1) and (4).
(5) Put the duct (2) is in position into the flexible sleeves (6).
(6) Make sure that the flexible sleeves (6) are in position between the two red markings.
(7) Install the clamps (5) and (7) on the sleeves (6).
(8) Install the clamp (3) that attach the duct (2) to the structure.
(9) Make sure that the distance between the two red markings of the ducts (1), (2) and (4) is 90 +5 mm or -5 mm (3.5433 +0.1969 in. or -0.1969 in.).
(10) Tighten the clamps (3), (5) and (7).
Subtask 21-26-42-865-064-A (1) Make sure that the parts retained from the removed component are clean and in the correct condition.
(2) Make sure that the clamps (3), (5) and (7), the flexible sleeves (6) and the ducts (1), (2) and (4) are in the correct condition.
(3) Remove the PLUG-BLANKING from each disconnected line end.
(4) Install the flexible sleeves (6) on the ducts (1) and (4).
(5) Put the duct (2) is in position into the flexible sleeves (6).
(6) Make sure that the flexible sleeves (6) are in position between the two red markings.
(7) Install the clamps (5) and (7) on the sleeves (6).
(8) Install the clamp (3) that attach the duct (2) to the structure.
(9) Make sure that the distance between the two red markings of the ducts (1), (2) and (4) is 90 +5 mm or -5 mm (3.5433 +0.1969 in. or -0.1969 in.).
(10) Tighten the clamps (3), (5) and (7).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 21-26-42-710-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | AIR COND/AVNCS VENT/CTL | 6HQ | D06 |
| 49VU | AIR COND/AVNCS VENT/CTL | 5HQ | D05 |
| 122VU | AIR COND/AVNCS/VENT/MONG | 3HQ | Y17 |
| ** ON A/C NOT FOR ALL | |||
| 123VU | AVNCS VENT/EXTC/FAN | 2HQ | AE02 |
| ** ON A/C ALL | |||
| 123VU | AVNCS VENT/BLOWER/FAN | 1HQ | AD10 |
| ** ON A/C NOT FOR ALL | |||
| 123VU | AVNCS VENT/EXTC/FAN | 2HQ | AC04 |
C. Operational Test
(1) Do an operational test of the avionics equipment ventilation-system (Ref. AMM TASK 21-26-00-710-001):
(a) By hand make sure there is no leak on the connection you install.
5. Close-up(1) Do an operational test of the avionics equipment ventilation-system (Ref. AMM TASK 21-26-00-710-001):
(a) By hand make sure there is no leak on the connection you install.
NOTE: Leaks are not permitted.
(b) Stop the operational test. Subtask 21-26-42-410-062-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the forward cargo-compartment sidewall-panels 131HW and 131GW (Ref. AMM TASK 25-54-12-400-003).
(3) Install forward cargo-compartment partition-panels 131DW and 131CW (Ref. AMM TASK 25-54-11-400-001).
(4) Close the forward cargo-compartment door (Ref. AMM TASK 52-30-00-860-001).
(5) Remove the access platform(s).
Subtask 21-26-42-862-061-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the forward cargo-compartment sidewall-panels 131HW and 131GW (Ref. AMM TASK 25-54-12-400-003).
(3) Install forward cargo-compartment partition-panels 131DW and 131CW (Ref. AMM TASK 25-54-11-400-001).
(4) Close the forward cargo-compartment door (Ref. AMM TASK 52-30-00-860-001).
(5) Remove the access platform(s).
Avionics Equipment Blowing-Duct