W DOC AIRBUS | AMM A320F

Clean Cockpit Air Supply Ducting Grid


TASK 21-21-49-100-001-A
Clean Cockpit Air Supply Ducting Grid


WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 131
1. Reason for the Job
Refer to the MPD TASK: 212100-01
CLEAN COCKPIT AIR SUPPLY DUCTING GRID

2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 2M (6 FT)
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.08BAA9)
Non Aqueous Cleaner-General - -
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
131
FORWARD CARGO COMPARTMENT
825
131MW
131SW
131PW
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 12-33-21-618-001-A
Pre-conditioning through the LP Ground Connection (Aircraft Electrical Power Available)
TASK 12-33-21-618-001-A-01
Pre-conditioning through the HP Ground Connection
TASK 12-33-21-618-001-A-02
Pre-conditioning with the APU
TASK 12-33-21-618-002-A
Pre-conditioning through the Low Pressure SUBFREEZING PCA GROUND-AIR SUPPLY
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 25-54-12-000-001-A
Removal of the Forward Cargo-Compartment Partition
TASK 25-54-12-000-003-A
Removal of the Sidewall Panels in the Forward Cargo Compartment
TASK 25-54-12-400-001-A
Installation of the Forward Cargo-Compartment Partition
TASK 25-54-12-400-003-A
Installation of the Sidewall Panels in the Forward Cargo Compartment
TASK 52-30-00-860-001-A
Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 52-30-00-860-002-A
Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
F Cockpit Air Supply Duct Grid ** ON A/C NOT FOR ALL
F Cockpit Air Supply Duct Grid ** ON A/C NOT FOR ALL
F Cockpit Air Supply Duct Grid ** ON A/C NOT FOR ALL
3. Job Set-up
Subtask 21-21-49-861-050-A
A. Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 21-21-49-010-050-A ** ON A/C NOT FOR ALL
B. Get Access
   (1) Put the ACCESS PLATFORM 2M (6 FT) in position at the FWD cargo-compartment door 825.
   (2) Open the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
   (3) Remove access panel 131MW (Ref. AMM TASK 25-54-12-000-003).
Subtask 21-21-49-010-050-B ** ON A/C NOT FOR ALL
B. Get Access
   (1) Put the ACCESS PLATFORM 2M (6 FT) in position at the FWD cargo-compartment door 825.
   (2) Open the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
   (3) Remove the sidewall panel 131SW (Ref. AMM TASK 25-54-12-000-003).
Subtask 21-21-49-010-050-D ** ON A/C NOT FOR ALL
B. Get Access
   (1) Put the ACCESS PLATFORM 2M (6 FT) in position at the FWD cargo-compartment door 825.
   (2) Open the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-001).
   (3) Remove access panel 131PW (Ref. AMM TASK 25-54-12-000-001).
4. Procedure
Subtask 21-21-49-020-050-A
A. Removal of the Duct
   (1) Remove the clamps (2).
   (2) Remove the duct (1).
Subtask 21-21-49-110-050-A
B. Clean the grid
   (1) Clean the grid (3) with Non Aqueous Cleaner-General - - (Material No.08BAA9) .
Subtask 21-21-49-420-050-A
C. Installation of the Duct
   (1) Install the duct (1).
   (2) Install the clamps (2).
Subtask 21-21-49-710-050-A
D. Test(s)
   (1) Do the pre-conditioning through the LP ground connection (Ref. AMM TASK 12-33-21-618-001).
or
Do the pre-conditioning through the HP ground connection (Ref. AMM TASK 12-33-21-618-001).
or
Do the pre-conditioning through the APU (Ref. AMM TASK 12-33-21-618-001).
or
Do the pre-conditioning through the LP SUBFREEZING PCA GROUND-AIR SUPPLY (Ref. AMM TASK 12-33-21-618-002).
   (2) Do the leak check of the duct connections.
   (3) Make sure that there are no leaks.
   (4) Stop the pre-conditioning through the LP ground connection (Ref. AMM TASK 12-33-21-618-001).
or
Stop the pre-conditioning through the HP ground connection (Ref. AMM TASK 12-33-21-618-001).
or
Stop the pre-conditioning through the APU (Ref. AMM TASK 12-33-21-618-001).
or
Stop the pre-conditioning through the LP SUBFREEZING PCA GROUND-AIR SUPPLY (Ref. AMM TASK 12-33-21-618-002).
5. Close-up
Subtask 21-21-49-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install access panel 131MW (Ref. AMM TASK 25-54-12-400-003).
   (3) Close the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
   (4) Remove the access platform(s).
Subtask 21-21-49-410-050-B ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the sidewall panel 131SW (Ref. AMM TASK 25-54-12-400-003).
   (3) Close the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
   (4) Remove the access platform(s).
Subtask 21-21-49-410-050-D ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install access panel 131PW (Ref. AMM TASK 25-54-12-400-001).
   (3) Close the FWD cargo-compartment door 825 (Ref. AMM TASK 52-30-00-860-002).
   (4) Remove the access platform(s).
Subtask 21-21-49-862-050-A
B. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
[Rev.10 from 2021] 2026.04.02 06:10:55 UTC