Installation of the Third (Fourth) Occupant Individual Air-Outlet
TASK 21-21-44-400-002-A
Installation of the Third (Fourth) Occupant Individual Air-Outlet
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 21-21-44-860-051-A
Subtask 21-21-44-420-052-B
Subtask 21-21-44-865-055-A
[Rev.10 from 2021]
2026.04.02 06:10:55 UTC
Installation of the Third (Fourth) Occupant Individual Air-Outlet
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 211 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
Subtask 21-21-44-860-051-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
Subtask 21-21-44-865-054-A (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 122VU | AIR COND/RECIRC FAN/L/CTL | 2HG | X20 |
| 122VU | AIR COND/RECIRC FAN/L/SPLY | 1HG | X18 |
Subtask 21-21-44-420-052-B
A. Installation of the Third Occupant Individual Air-Outlet
(1) Put the air outlet (2) in position on the duct (1).
(2) Put the duct (1) with the air outlet (2) in position on the plate (4).
(3) Install the 4 screws (8) and tighten.
(4) Put the plate (4) in position on the frame (3). Tighten the 4 quarter-turn fasteners (5).
(5) Put the lining panel (6) in position. Install the 4 screws (7) and tighten.
5. Close-up(1) Put the air outlet (2) in position on the duct (1).
(2) Put the duct (1) with the air outlet (2) in position on the plate (4).
(3) Install the 4 screws (8) and tighten.
(4) Put the plate (4) in position on the frame (3). Tighten the 4 quarter-turn fasteners (5).
(5) Put the lining panel (6) in position. Install the 4 screws (7) and tighten.
Subtask 21-21-44-865-055-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 21-21-44-862-051-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 122VU | AIR COND/RECIRC FAN/L/CTL | 2HG | X20 |
| 122VU | AIR COND/RECIRC FAN/L/SPLY | 1HG | X18 |
Third (Fourth) Occupant Individual Air-Outlet